Phase 6 - Testing

Purpose

Validate the integrated change against the expected behavior and risk.

Entry criteria

  • The change is integrated or ready for test validation

Required inputs

  • Integrated code or package
  • Test plan or expected checks

Activities

  • Run automated tests
  • Perform additional verification where needed
  • Review failures and fix defects before proceeding

Engineering responsibilities

  • Ensure testing covers the relevant risk surface

AI-agent responsibilities

  • Execute approved tests and report outcomes
  • Avoid claiming success without actual validation

Required artifacts

  • Test results
  • Failure analysis if needed

Validation

  • Required tests pass or approved exceptions exist

Exit criteria

  • Testing is complete enough for release candidate preparation

Approval or gate

  • Testing gate

Handoff

  • Move to Phase 7 - Release Candidate